Dr. D's Cliffhanger (Update 3), Lone Star Lil's, Crackaxle Canyon Refresh
Front Gate Ticket Booths
The ticket booths near the park’s front gate have been completely removed and new pavers have been installed.
Crackaxle Canyon Refresh
The Coca-Cola Freestyle location in Crackaxle Canyon has received a paint job. The inside, however, has been completely cleared out. Ground work is also taking place in front of the building.
Dr. Diabolical’s Cliffhanger
Construction has begun on the transfer shed for Dr. Diabolical’s Cliffhanger.
Installation of the ride’s track has also begun.
Ride footers have been poured throughout the former location of Sundance Theatre.
A look at the transfer shed and first track install as seen from the park’s Crackaxle Canyon area.
The former Totally Kickin’ Chicken restaurant has been completely demolished to make way for Dr. Diabolical’s Cliffhanger.
Work continues near the former location of Sundance Theatre.
More footer work continues behind Lone Star Lil’s Amphitheater.
Lone Star Lil’s Amphitheater
Lone Star Lil’s Amphitheater will feature a new paint job in time for the park’s 30th anniversary celebration.
The venue’s seats have been removed to paint ceiling beams and will be reinstalled once work is complete. Dr. Diabolical’s Cliffhanger also makes its first appearance in the background.